Facing a December 11 cost estimate that will go to voters in April, the Peaslee School design subcommittee spent more than two hours on Friday looking for savings. Members agreed to price the athletic field as a plain grass lawn, to aim for a 30 to 35 percent cut in walkways, and to question an elevated loading dock and the plan for 145 parking spaces. A pre-K classroom has already been dropped from the program. The sharpest disagreement was about the roof: the architect defended gables as a familiar New England touch, while Kevin Wyrsch said it was "hard for me to get behind" adding gables just for the sake of having them.
Site cuts: grass field, fewer walkways, loading dock in question
Watch: 0:10:00–0:59:59
With estimators already pricing the project, Kent opened the site review by asking what he called "easy targets." The first was a suggestion from Jake: leave out the baseball field with its soccer overlay and dugouts, and instead seed "a big giant grass field" with proper drainage. Kent said most of the cost sits in the infield, the dugouts and the irrigation (0:13:31).
Jake called it a school decision but backed pricing it. A separate dollar figure, he said, "gives us a really concrete number for CPC" in case the Community Preservation Committee wants to pay for a full athletic field (0:19:08). Tristan warned that a field used for youth sports would need irrigation. He noted that Zeh is the only district school field with it, Lincoln "turns into a dust bowl" and, in Jake's words, Proctor and Peaslee are "mud pits" (0:14:22).
Becky Pellegrino asked how an add alternate would work with the state school building authority (MSBA) and town meeting. Kent explained the choice: the December 11 estimate goes to voters in April, so the board can either carry everything now or "trim back a little bit" and add items back as bid alternates later (0:22:15). Tristan favored trimming: "we're trying to get the budget as tight as we can" ahead of "a difficult town vote" (0:24:05).
The group pushed further. Tristan said the town doesn't need to "pave the shortest path from everywhere to every other place," and Kent set a target of a 30 to 35 percent cut in walkways, keeping concrete for now (0:40:42). Tristan also challenged the elevated loading dock, saying other elementary schools don't have one, and it went on the list for a talk with facilities staff (0:27:54). A suggestion to merge the pre-K and main playgrounds got no support. Jake and Mary Coakley said separate areas are safer and make recess easier to schedule.
Fencing stayed in. Mary Coakley said her own school has no fencing and "there are definitely complications," but added "you don't want it to feel like a prison either" (0:37:03). The group settled on a 4-foot fence on the three sides that face roads, left open toward the school. Kent said each of these ideas needs engineered drawings before the estimators can price it.
- “the site is is not reimburseed as much as the building” — Kent (0:59:51)
- “aesthetically it might be nicer without the fence, but for kids safety and knowing that there's a loop road, like you're just waiting for something to happen” — Kevin Wyrsch (0:33:33)
- “walking around a corner is is not a big deal. It's not a huge site.” — Tristan (0:40:42)
Gables or flat roofs? Members question the design direction
Watch: 1:42:35–2:15:57
Jennifer showed several massing options. The starting design has gabled and sloped roofs over the front-facing spaces. A second option trades some of the slopes over the classroom wings for light monitors that would brighten the team commons areas.
Jake said the gables were "starting to feel a little forced," and that one version "almost seems like it wants to be all flat roofs" (1:45:46). Kevin Wyrsch asked whether the team had worked out design principles and "basic success criteria" before settling on gables (1:55:47). He pointed to the firm's own flat-roofed Ashland school, saying it "looks inviting. It looks safe. It looks cost-effective" (2:04:29).
Kent defended the approach. The planning board representative wanted "a New England feel," he said, and a local men's club asked about slope roofs to reduce maintenance. He argued that a gable must "have a function" and that the firm doesn't design decoration (2:10:24). He estimated that cutting sloped roof area from about 50 percent to 30 percent could save $300,000 to $400,000 (1:58:56).
Kevin Wyrsch wasn't convinced: "it's just hard for me to get behind the let's just stick a gable on to stick a gable on" (2:08:24). Jake said he had no strong preference either way. He doubted that Northborough's architecture "really adheres itself to gable roofs," suggested the push came from "an older generation" in the groups consulted, and added that none of the town's schools have them (2:13:19). Tristan asked for eye-level views from the street, since "nobody's going to fly a drone and see the roofs" (1:52:54).
The architects agreed to bring back a design-principles and precedent presentation, eye-level perspectives and an all-flat option. Kent said the direction should be fairly set during schematic design but can still change in design development.
- “if if we're going to do a gable, it has to have a function” — Kent (2:10:24)
- “how we can build consensus that can stand the test of scrutiny” — Kevin Wyrsch (2:04:30)
- “I think you're still going to make a nice building without a flat roof” — Jake (2:14:04)
Is 145 parking spaces too many? EV chargers also questioned
Watch: 0:43:17–0:56:23
The architects are planning for about 145 parking spaces, based on the average at four similar elementary schools. Code also requires EV provisions: Jennifer said the choice is charging stations at eight spaces or "EV ready" wiring at about 15 (0:44:17). Kent recommended building only what code requires for now, since EV-ready means running wire, not just empty conduit.
Tristan asked whether the chargers could be pay stations: "as a taxpayer I wouldn't be in favor of" the district paying to charge people's cars (0:46:52). The architects said they would check.
Tristan then challenged the parking total. Parallel parking along the 24-foot loop road could absorb overflow at big events, he said, so the school might drop or shrink a whole bank of spaces. That would also reduce paving, stormwater work and the EV requirement (0:50:26). Mary Coakley said the school uses about 70 spaces a day. Kent said police and fire had been open to perimeter parking. He agreed the spaces next to the bus loop were "a good target" but wants the district to weigh in (0:55:35).
- “I think 145 sounds sounds high to me in terms of fixed spaces” — Tristan (0:56:12)
- “there's some towns who put these in that said, I wish we never put these in.” — Kent (0:46:26)
Pre-K cut to four classrooms
Watch: 0:02:23–0:09:00
Jennifer said changes to the space program, mainly shrinking pre-K from five classrooms to four plus trimming food service and office space, have cut just under 3,500 square feet once a grossing factor is applied.
Jake pushed back on the pre-K cut. Five rooms had been planned to allow for growth, he said, and he questioned cutting the cost "at the expense of future town growth" in a building meant to last 50 years (0:05:37).
Mary Coakley said four rooms match what the district uses today, and that the goal is not a preschool center. Becky Pellegrino said historical special education data supports three integrated classrooms and one ABA room, and that any future growth could use space in other buildings (0:07:27). No other program categories changed.
- “based on historical data and our current needs, the three classrooms with the one ABA classroom um is sufficient” — Becky Pellegrino (0:08:12)
Other business
Call to order and minutes
Watch: 0:00:22–0:02:10
Kevin Wyrsch opened the meeting at 10:06 a.m. with two of the three members present, enough for a quorum. The November 2 minutes were approved by roll call.
- Motion: Approve minutes of the November 2, 2026 meeting — Passed 2-0 (roll call) (0:01:07)
Floor plan updates
Watch: 1:00:40–1:42:29
The main entry now sits in the middle of the building, between the community spaces and the classroom wings, with a matching north vestibule for accessible parking. The restrooms no longer face the entrance, which Jake welcomed. On the second floor, the media center and art room have swapped places.
The architects will test moving kindergarten upstairs to create lower- and upper-elementary wings, which could shrink the team commons. Tristan asked that any commons be truly usable, not "a rotary" of people passing through (1:16:35). Jake asked whether a commons could become a classroom later. The architects said special education rooms must stay centrally located.
Members rejected cutting tile wainscoting for now. Tristan said laminate tends to bubble and "it is not the place to skimp" (1:09:13). However, lowering the tile from four feet to three may be considered later. The gym keeps its maple floor, while a synthetic floor for the stage is open for discussion.
Lockdown doors are integrated electronically and included in the budget. Operable classroom windows, opened no more than 4 inches, were deferred to the design development phase. Kevin Wyrsch asked the team to keep the central stair open if code allows.
Public comment and adjournment
Watch: 2:15:57–2:16:42
No one from the public spoke. Next, the architects will study the floor plan stacking, prepare value-engineering exhibits and a precedent board, and bring back eye-level views of the building.
- Motion: Adjourn — Passed 3-0 (roll call) (2:15:57)
Who spoke
- Kent (likely), the project architect — 54 min, 43 sec, 55% of speaking time, 471 turns
- Tristan (likely), a design subcommittee member — 15 min, 28 sec, 16% of speaking time, 88 turns
- Jennifer (likely), a project architect — 8 min, 30 sec, 9% of speaking time, 105 turns
- Kevin Wyrsch (likely), the chair — 7 min, 25 sec, 7% of speaking time, 62 turns
- Jake (likely), a design subcommittee member — 7 min, 23 sec, 7% of speaking time, 65 turns
- Mary Coakley, Peaslee Elementary School Principal — 3 min, 30 sec, 4% of speaking time, 27 turns
- Becky Pellegrino, School District Finance Director — 1 min, 33 sec, 2% of speaking time, 5 turns
- Karina Pena, OPM, Peasley School Project — 1 min, 5 sec, 1% of speaking time, 9 turns
Possible Open Meeting Law issues
Any Open Meeting Law issues found for this meeting will be posted after the 30-day complaint period ends on December 13, 2026.
See the Open Meeting Law page on Mass.gov for information on the Open Meeting Law.
Summary last updated Nov 14, 2026 at 1:19 PM.