Fire Station Building Committee ·
Fire station building committee member warns of moisture, exposed foam and site mess as schedule slips
Fire Station Building Committee, October 28, 2026
Meeting summary · Northborough. Written from the meeting's automatically-generated transcripts; names come from voice recognition and may be incomplete. Names in italics are likely but not yet confirmed.
Northborough's new fire station is set to be closed in against the weather in mid-to-late November. Before that happens, Tom pressed the project team about water in the open building, roof foam insulation left exposed, and what he called clear OSHA violations on site. The owner's project manager said the contractor is answering each point. Members also began planning the building's dedication plaque, leaning toward a short design honoring the town's firefighters. The committee voted on minutes and adjournment only. The agenda listed possible change orders, but none came up for a vote.
Member's concerns: moisture, exposed foam and site safety
Watch: 1:02:41–1:06:20
The sharpest exchange came under "questions asked." Dawn noted that Tom had sent in written questions, and he went through them in public (1:02:53).
His first concern was "the slippage in the construction schedule" while crews work on several systems in a building that is not yet weather tight. Colder weather makes a building harder to dry out, he said, and finishes like drywall go in, "the possibility of getting mold trapped into the wall systems is difficult to remedy."
He also questioned the closed-cell spray foam left exposed on the roof. The spec allows 90 days of exposure, but he said every other manufacturer he knows, naming Carlisle and Johns Manville, allows 30. "That's why alarm bells were going off," he said, warning that discolored foam loses insulating value and can pull away from the substrate (1:03:40). On conditions inside the building he was blunt: "OSHA violations are clearly apparent" (1:04:07).
The owner's project manager said the contractor reported that day that it had brought on a laborer for cleanup. The foam is due to be covered starting Monday, close to the 90-day mark around November 1 (1:04:31). Tom said installation began in late August or early September. The project architect offered to verify the date, and the owner's project manager pointed to daily field reports and photos.
The owner's project manager said he had raised the same water concern weeks earlier. The contractor, he said, has agreed to squeegee and remove standing water before sealing the building rather than "leave the moisture on the slabs" (1:05:38). Members will check on progress at next week's site walk.
- “So, they really need to cover that up and not try to go to 90 days, because we're already in 60 days.” — Tom (1:02:53)
- “the general mess inside the building, it's not safe. especially for us non-construction types” — Tom (1:04:07)
- “they did acknowledge that the building needed to be dried out as it approaches its watertight date” — the owner's project manager (1:05:38)
Dedication plaque: who gets named?
Watch: 0:54:43–1:01:35
The project architect asked for direction on the dedication plaque, the one sign not yet submitted. She showed examples from other buildings, ranging from crowded plaques that list committees, officials and staff to Ashland's simple one, which names only the building committee, the select board and the project team (0:57:20).
Dawn offered her view: the building should be dedicated "to all previous and current" and future firefighters in Northborough (0:58:20). Tom suggested copying the library plaque's format so buildings look consistent, but with content closer to Ashland's: "less information, the better."
Dan said it would be nearly impossible to fairly recognize everyone involved over "the last nine years," including some "that are no longer with us." Naming them all, he said, would make the plaque "enormous." Mike Tietjen backed dedicating the building "to the men and women who work in it," possibly with a statement about the fire profession.
The group settled on "kind of minimal," with the design team included. The project architect will draft a few options. Dan will send her photos of the plaque at the Lincoln Street School.
- “I like the idea, dawn, of dedicating the building to the men and women who work in it.” — Mike Tietjen (0:59:37)
- “It'd be impossible. The thing would be enormous.” — Dan (0:59:26)
Other business
Executive session and minutes
Watch: 0:00:27–0:44:39
The committee went into executive session to discuss bargaining or litigation strategy related to the construction timeline. The town's financial planning liaison, a non-voting member, joined them. Open session resumed at about 6:44 p.m. The October 14 minutes were approved as written on a motion by Dan.
- Motion: Approve October 14, 2026 meeting minutes as written — Passed (voice vote) (0:44:32)
Construction update
Watch: 0:44:46–0:50:19
The owner's project manager reported that the exterior sheathing and air vapor barrier are done. So are the interior framing on the administration side and the masonry block for the apparatus bay utility rooms and mezzanine. Nearly all Route 20 infrastructure is in.
Night work is nearly finished. One night next week will close a lane for the sidewalk corner by the Hillside Grill (0:46:12). Two more nights of Route 20 milling and paving, with a detour, are pending DOT approval (0:46:47).
Revised weather-tight dates are November 13 for the administration building and November 20 for the apparatus bay (0:47:39). Bricklaying and roofing both start Monday, November 2. Windows are in storage and will go in after the brick, likely in December or January. Until then, the openings will be covered with plastic.
Schedule update
Watch: 0:50:19–0:51:54
Brick will wrap the building starting at the administration side. The binder course of pavement on the east side is scheduled for October 29. The new sidewalk will run from the neighboring bank to the Hillside property line, and drainage will be tied in under the future apparatus bay apron. No change order was presented.
Financial update
Watch: 0:52:01–0:54:40
The owner's project manager dropped the "additional need" line from the financial report and moved that money back into contingency. Column G now shows remaining contingency plus bid savings. A committee member said the change helps the finance department see that new change orders don't dip into bid savings.
Total paid to date stands at 18.4 (no unit given in the captions). Excluding bid savings, about $685,000 remains in contingency (0:54:13). No change order was voted.
Furniture and equipment
Watch: 1:01:39–1:02:38
Office furniture drawings are being revised and will be reviewed with the fire department. Firefighters will visit stations using the proposed recliners and test chair samples.
Next meetings and adjournment
Watch: 1:06:20–1:07:29
The site walk stays at 4 p.m. on November 4 because the clocks change and daylight is short. The regular meeting is November 18. There was no public comment. The meeting adjourned at 7:07 p.m.
- Motion: Adjourn — Passed (voice vote) (1:07:21)
Who spoke
- Unidentified speaker (S1), the owner's project manager — 6 min, 7 sec, 35% of speaking time, 55 turns
- Unidentified speaker (S2), the project architect — 4 min, 10 sec, 24% of speaking time, 19 turns
- Dawn (likely), the chair — 2 min, 32 sec, 14% of speaking time, 32 turns
- Tom (likely), a building committee member — 2 min, 5 sec, 12% of speaking time, 26 turns
- Unidentified speaker (S5), a committee member — 1 min, 12 sec, 7% of speaking time, 9 turns
- Mike Tietjen, Select Board Vice Chair — 57 sec, 5% of speaking time, 9 turns
- Dan (likely), a building committee member — 32 sec, 3% of speaking time, 7 turns
Possible Open Meeting Law issues
Any Open Meeting Law issues found for this meeting will be posted after the 30-day complaint period ends on November 27, 2026.
See the Open Meeting Law page on Mass.gov for information on the Open Meeting Law.
Summary last updated Nov 14, 2026 at 3:03 PM.