Fire Station Building Committee ·
Fire station roof delayed to Sept. 18 as Route 20 night work begins
Fire Station Building Committee, August 26, 2026
Meeting summary · Northborough. Written from the meeting's automatically-generated transcripts; names come from voice recognition and may be incomplete.
Northborough's new fire station won't be sealed against the weather until September 18, the project manager told the Fire Station Building Committee, after the roofer ran short of workers during the summer rush. Night work on Route 20 starts Monday, and the repaving is set to finish just before asphalt plants close for the winter. The committee approved an $8,331.67 change order for removing extra boulders and was told contingency funds still cover about $1.4 million in expected costs. The short meeting went smoothly and ended with a vote to go into executive session on the construction timeline.
Roofing delay pushes weathertight date to Sept. 18
Watch: 0:01:41–0:06:09
The project manager said the most important event of the month was the committee's August 12 site walk-through. Members saw the block retaining wall and toured the inside of the building. The south section of the retaining wall is nearly complete, and crews will turn next to the west side and the detention basin.
Exterior framing and sheathing are up, and a liquid-applied vapor barrier is going on. The stair tower is in place. Electrical, plumbing and mechanical trades have started rough-in work on materials that can safely get wet. In the apparatus bay, crews have built the block utility and storage rooms and the wall separating the bay from the administration side.
Roofing, however, is "on a little bit of a hold." When a committee member asked what had happened to the weathertight completion date (0:04:51), the project manager answered that it "is now September 18th," which covers the exterior sheathing and the roof (0:04:58).
According to the discussion, the roofer had "manpower issues" because contractors were racing to finish summer jobs before school started. A committee member said the roofers should start Monday and finish within two weeks (0:05:55). Once the roof is on, the project manager said, the inside trades can work "without fear of water."
- “They expect the roofers to be back on site in the next couple of weeks and wrapping up the roof” — the project manager (0:03:16)
Route 20 night work starts Monday; paving deadline is tight
Watch: 0:06:14–0:10:30
The street work on Route 20 starts Monday evening, the project manager said. The first job is crossing the road to install a manhole in front of the site trailers. Expect lane closures and shifts from 9 p.m. to 5 a.m. for about five days next week (0:06:16).
A committee member asked whether signs could go up at the site so drivers could plan around that week (0:07:27). A project team member said he would have to ask, since it is Route 20. He added that crews "got some pushback" for construction signs they had already put up (0:07:54). Members agreed to follow up the next morning.
The project manager said the street work comes to a little more than two weeks of night work, split into two stretches with daytime lane-closure work in between. The second stretch covers the north side near Dunkin' Donuts. The final mill and overlay is slated for late October.
The chair asked whether that schedule keeps the project away from the November 12 date (0:09:14). The project manager said it would be "right up against" the "last few days before the asphalt plants close for the winter." Masonry has no start date yet. It will begin once the vapor barrier is in place.
- “we can expect next week's work week to be the start of the Route 20 work and and lane shifting at night 9:00 p.m. to 5:00 a.m.” — the project manager (0:06:16)
Contingency holds as $1.4 million in costs looms; boulder change order approved
Watch: 0:10:30–0:16:00
The project manager presented a condensed financial report. About $16 million has been paid to date, including contractor payments and soft costs such as the project manager, architect and testing fees. Contingency "still remains healthy" and bid savings have not been touched (0:11:17).
About $1.4 million in work is planned but not yet under contract. Much of it is a large proposed change order for the Route 20 street work, which has not been finalized. Possible contaminated soil where the trailers are parked is also on the list. Those costs would be covered by the roughly $1.94 million left in contingency.
The project manager also handed out formal change order number nine, which bundles the three proposed change orders the committee agreed to last month, for $11,936.93. Members briefly discussed whether they had already voted on those, and the project manager said they had.
A new proposed change order, number 27, came to $8,331.67 for removing extra boulders from the south retaining wall. The contract covered up to 100 yards of boulder removal, a limit the project passed about a year ago. "This is thankfully boulders and not ledge," The project manager said (0:15:05). The committee approved it.
- Motion: Approve proposed change order 27 for $8,331.67 for removal of additional boulders — Passed (captions give the tally as 9-0) (0:15:46)
- “We haven't really had to address boulders in quite a while, so I just wanted to bring this to your attention.” — the project manager (0:14:58)
Other business
Announcements and minutes
Watch: 0:00:20–0:01:41
The chair announced that the vice chair has resigned from the committee because of increasing professional obligations. A new vice chair will be elected at the next meeting. A Financial Planning Committee member will serve as a non-voting liaison, and a town representative named Stephanie sat in for an absent town official, also without a vote.
The committee moved to accept the July 22 minutes.
- Motion: Approve the July 22, 2026 minutes — outcome unclear (0:01:34)
Design update: furniture tour
Watch: 0:16:02–0:17:10
The project architect said the design team is still answering contractor questions from the field. Along with the fire department, the team toured AIS's office furniture showroom and factory in Leominster, hosted by W.B. Mason. W.B. Mason has done work for the town before, including for the police department. More conversations are needed about furniture for other parts of the building.
Questions, public comment and future dates
Watch: 0:17:10–0:18:10
There were no public comments and no other business. The next site walk is September 9 at 4 p.m., and the monthly meeting is September 23.
Executive session on construction timeline
Watch: 0:18:10
The committee moved to go into executive session to discuss bargaining or litigation strategy over the construction timeline, followed by a roll call vote. The agenda says the committee would not come back into open session afterward.
- Motion: Enter executive session to discuss strategy regarding collective bargaining and/or litigation over the construction timeline — outcome unclear (roll call) (0:18:43)
Who spoke
- Unidentified speaker (S1), the project manager — 8 min, 19 sec, 67% of speaking time, 48 turns
- Unidentified speaker (S2), the chair — 1 min, 51 sec, 15% of speaking time, 31 turns
- Unidentified speaker (S3), the project architect — 55 sec, 7% of speaking time, 5 turns
- Unidentified speaker (S4), a committee member — 46 sec, 6% of speaking time, 12 turns
- Unidentified speaker (S5), a project team member — 29 sec, 4% of speaking time, 10 turns
Possible Open Meeting Law issues